Construction Works on the Herat Section of the TAPI Project Near Completion

kamran2_admin
Sat, Nov 28 2026 3:16 PM
تاپی

Construction works on the Herat section of the (TAPI) Gas Pipeline Project have made significant progress, with approximately 92 percent of the work completed to date.
According to available information, out of the total 150-kilometre length of the project within Afghanistan, 142.9 kilometers of pipeline have been laid and welded, leaving only 8 kilometers remaining.
Meanwhile, the installation of essential pipeline equipment and the construction of related facilities have also made considerable progress. 
Construction of the Gas Offtake Station and the Gas Metering Station in Guzara District of Herat Province has also reached approximately 55 percent completion.
Furthermore, hydro testing has been completed along approximately 70 kilometers of the laid pipeline, while testing of the remaining sections is underway at various stages. In addition, the installation of valves along the pipeline and the construction of crossings have been completed.
The Ministry of Mines and Petroleum, in cooperation with TAPI Pipeline Company Limited, is making joint efforts to complete the works on this major regional project in accordance with the established schedule by the end of the current Gregorian year.
Meanwhile, the survey of secondary pipelines and related facilities for the development of the internal gas distribution and regulation network in Herat City has also been completed. Efforts are underway to commence the practical implementation of the network construction works as soon as possible.
The TAPI Project is regarded as one of Afghanistan's significant projects for promoting economic growth, ensuring energy supply, creating employment opportunities, and strengthening regional cooperation.

Latest news

Sat, Nov 28 2026 3:16 PM
Background image

Construction Works on the Herat Section of the TAPI Project Near Completion

Construction works on the Herat section of the (TAPI) Gas Pipeline Project have made significant progress, with approximately 92 percent of the work completed to date.
According to. . .

Thu, Nov 26 2026 3:25 PM
Background image

Construction Work on the Yatim Taq Cement Project in Jawzjan Province Progressing Rapidly

In accordance with the agreement signed between the Ministry of Mines and Petroleum and the 77 Turkish Construction Company, the exploration work for the Yatim Taq Cement Project in. . .

Tue, Oct 06 2026 10:36 PM
Background image

Deputy Minister for Policy and Programs Meets with Iran’s Deputy Foreign Minister for Economic Diplomacy

Mr.Abdul Rahman Qanit, Deputy Minister for Policy and Programs of the Ministry of Mines and Petroleum, met with Hamid Qanbari, Deputy Foreign Minister for Economic Diplomacy of the. . .

BACK TO NEWS